Notification of Works – Fairways Park Stage 1 – Lot 902, Fairway Drive, Kensington Grove​

Lockyer Valley Regional Council recently received funding support from the Australian and Queensland Governments to construct a new recreational park at Lot 902, Fairway Drive, Kensington Grove.  Fairways Park will be inclusive of all abilities, support family and community gatherings, offer exciting experiences for children and, in time, encourage growth of local sports.

The construction of Fairways Park Stage 1 is programmed to start at the end of October 2020, with works to be completed by July 2021, weather permitting.

Stage 1 of the project involves the construction of innovative playground facilities with multiple elements, a learn to ride course with imitation road signage, picnic facilities including shelters and barbeques, public amenities, formal and informal paths/footpaths, dog park and more.

Due to the size of this project, it is expected there will be an increase in dust and noise during the construction period.  All measures will be taken to reduce this as much as possible. Appropriate environmental management will also be in place to protect and preserve wildlife.

Construction signage will be present to ensure the safety of workers and the public.  Due to the increase of traffic during the construction period, a reduction of speed limits will be considered as part of the Traffic Management Plan.  Please adhere to roadwork signage, detours and any instructions issued.

Council apologises for any inconvenience this work may cause and would like to thank you for your patience during construction.

For a detailed project overview, please contact our Customer Service Centre on 1300 005 872 or visit our Engagement Hub at lockyervalley.engagementhub.com.au​

Roa​ds​​

Notificiation of Construction Works - Woodlands Road and Rangeview Drive Intersection, Gatton

Lockyer Valley Regional Council would like to advise that the upgrading of Woodlands Road and Rangeview Drive intersection is programmed to commence on Tuesday 11 May 2021, weather permitting. The works involve widening the existing road formation, drainage, concrete kerb, bitumen surfacing and road furniture installation.

To facilitate these works the Woodlands Road and Rangeview Drive intersection will require changes to the current road conditions and may be reduced to one lane during the entire project. For the safety of road users and our onsite personnel, traffic management signage and controls will be in place for the duration of the project.

Works will generally be carried out Tuesday to Friday 7.00am to 4.00pm

Council anticipates that the project will take approximately 10 weeks. Access for affected property owners adjacent to the works will be available throughout the construction period.

Council apologises for any inconvenience this work may cause and would like to thank you for your patience during construction.

Notification of Construction Works – Postmans Ridge Road, Withcott​

Lockyer Valley Regional Council would like to advise that the upgrading of Postmans Ridge Road, Withcott between Withcott Seedling and Ashlands Drive is programmed to commence on Wednesday 14 April 2021, weather permitting. The works involve excavation of the existing road pavement, subgrade treatment, new road base, drainage works, bitumen seal and road furniture.

To facilitate these works Postmans Ridge Road will be reduced to one lane during the entire project. For the safety of road users and our onsite personnel, traffic management signage and controls will be in place for the duration of the project.

Works will generally be carried out Monday to Thursday 7.00am to 4.00pm

Council anticipates that the project will take approximately 12 weeks. Access for affected property owners adjacent to the works will be available throughout the construction period.

Council apologises for any inconvenience this work may cause and would like to thank you for your patience during construction.

Notification of Construction Works – Railway Street, Gatton​


Lockyer Valley Regional Council advises that the Railway Street asphalt overlay project, between
North street and Crescent Street is programmed to commence on Sunday afternoon at 6pm, 28
March 2021, weather permitting. The works involve minor pavement correction, profiling
operations, asphalt surfacing and line marking treatments.

To facilitate these works, Railway Street will be closed from Crescent Street to North Street,
inclusive of the North and Railway Street roundabout during the nights the works are to take place.
For the safety of road users and our onsite personnel, traffic management signage and controls will
be in place for the duration of the project.

Night works will be carried out from Sunday 28 March through to Wednesday 31 March 6.00pm to
6.00am, weather permitting.

Council anticipates that the project will take approximately 4 nights/shifts to complete. The road
corridor inclusive of all street parking and footpaths are to be closed during construction hours.
All vehicles will need to be removed from the area prior to 6pm on days of construction as the full
road width is required for construction. In the event Council can not find the owner of the vehicle
within a suitable timeframe, the vehicle may be towed at the owner’s expense.

Council apologises for any inconvenience this work may cause and would like to thank you for your
patience during construction.

Notification of Construction Works – Murphys Creek Road, Murphys Creek


Lockyer Valley Regional Council would like to advise that footpath construction works on Murphys
Creek Road, Murphys Creek are anticipated to commence on Monday 29 March 2021, and are
expected to take approximately 4 weeks to complete weather pending.

The project involves the construction of a new 330 metre concrete footpath on the northern side
of Murphys Creek Road, from the railway level crossing to the underpass.

Work will generally be performed between the hours of 7:00am and 4:00pm, Monday to Friday.

Construction signage and site delineations will be set up daily during the construction period.
Traffic management will be in place, these measures are to ensure the safety of workers and the
public. Please adhere to roadwork signage, detours and any instructions issued by Council
employees or the on-site contractor.

Council apologises for any inconvenience this work may cause and would like to thank you for your
patience during construction.

​​Notification of Construction Works – Beutels Road, Mt Whitestone​

Lockyer Valley Regional Council would like to advise that the upgrading of Beutels Road, Mt
Whitestone is programmed to commence on Wednesday 24 February 2021, weather permitting.
The works involve widening the existing road formation, road base placement and bitumen sealing.

To facilitate these works Beutels Road will be reduced to one lane during the entire project. For the
safety of road users and our onsite personnel, traffic management signage and controls will be in
place for the duration of the project.

Works will generally be carried out Monday to Thursday 7.00am to 4.00pm

Council anticipates that the project will take approximately two weeks. Access for affected
property owners adjacent to the works will be available throughout the construction period.

Council apologises for any inconvenience this work may cause and would like to thank you for your
patience during construction.

Notification of Construction Works – Laidley Recreation Reserve Entrance Upgrade​

Lockyer Valley Regional Council would like to advise that the upgrading of Whites Road, Laidley
from Patrick Street into the Laidley Recreational Reserve is programmed to commence on Tuesday
16th February 2021, weather permitting. The works involve widening the existing road formation
and drainage works to facilitate additional carparking at the Laidley Recreation Reserve.

To facilitate these works Whites Road will be reduced to one lane during work hours. For the safety
of road users and our onsite personnel, traffic management signage and controls will be in place
for the duration of the project. Additional carpark area will be provided during the project in lieu of
areas under construction, refer to the picture attached.

Works will generally be carried out Tuesday to Friday 7.00am to 4.00pm

Council anticipates that the project will take approximately 5 weeks. Access to the Laidley
Recreation Reserve, Ferarri Park and Anzac Park will be available throughout the construction
period.

Council apologises for any inconvenience this work may cause and would like to thank you for your
patience during construction.

​Notification of Construction Works - Spa Water Road, Iredale​

Lockyer Valley Regional Council would like to advise that the upgrading of Spa Water Road, Iredale

between Gierkes Road and Herrons Road is programmed to commence on Monday 18 January

2021, weather permitting. The works will involve widening the existing road formation and

drainage works.

To facilitate these works Spa Water Road will be reduced to one lane during the entire project. For

the safety of road users and our onsite personnel, traffic management signage and controls will be

in place for the duration of the project.

Works will generally be carried out Monday to Thursday 7.00am to 4.00pm Council anticipates that the project will take approximately 8 weeks. Access for affected property

owners adjacent to the works will be available throughout the construction period.

Council apologises for any inconvenience this work may cause and would like to thank you for your

patience during construction.

​Notification of Construction Works - Lake Clarendon Way, Lake Clarendon​

Lockyer Valley Regional Council would like to advise that the upgrading of Lake Clarendon Way, Lake Clarendon between Main Green Swap Road and Lester Road is programmed to commence on Tuesday 12 January 2021, weather permitting. The works will involve widening the existing road formation and drainage works.

To facilitate these works Lake Clarendon Way will be reduced to one lane during working hours. For the safety of road users and our onsite personnel, traffic management signage and controls will be in place for the duration of the project.

Works will generally be carried out Tuesday to Friday 7.00am to 4.00pm

Council anticipates that the project will take approximately 8 weeks. Access for affected property owners adjacent to the works will be available throughout the construction period.

Council apologises for any inconvenience this work may cause and would like to thank you for your patience during construction.

Facilities​​

​​Gatton Shire Hall - Upgrade works

PROJECT LOCATION: Gatton Shire Hall, 52 North Street, Gatton

PROJECT START DATE: 27 January 2021

ESTIMATED PROJECT FINISH DATE: by 31 August 2021

PROJECT OVERVIEW: ​
Gatton Shire Hall will undergo upgrade works to ensure the facility meets community needs and expectations well into the future using a combination of funding from Federal and State Governments and a contribution from Council.

Federal Government Building Better Regions Fund (BBRF) component:
(Funding - $439,350 ex GST and Council - $439,350 ex GST)
Foyer Refurbishment 
Mechanical Services Upgrade
Electrical switchboard/emergency lighting 
Communications upgrade 
Lower level fire compliance works 

State Government Building our Regions (BoR) component:
(Funding – $866,714 ex GST and Council - $88,300 ex GST)
Kitchen Refurbishment 
Eastern Courtyard Upgrade
Bar area extension and refurbishment 
Front entrance door work
Metalwork screening and northern courtyard sliding gate works
Northern Corridor Works
Old drinks bar storage room works
External cold-room

State Government COVID Works for Queensland (W4Q) component:
(Funding - $250,000 ex GST)
Roof Rectification Works
Roof Safety Works 

Contractor parking will be to the area adjacent to the green space (old Squash Courts site) to minimise interruption to any car parking in the main streets.

SIGNAGE: One (1) project sign and three (3) funding acknowledgement signs will be installed at the venue prior to works starting.

FAQs: 
Q: Who is the successful contractor that will be undertaking the upgrade works?
A: The successful contractor is McNab Developments (QLD) Pty Ltd.  McNab have significant experience with similar projects of this scale and will engage local contractors where possible for elevant parts of the project. 

Q: When will renovations commence?
A: On 27 January 2021, after the Australia Day Awards and Citizenship Ceremony has been held at the venue on 26 January 2021.

Q: How long will the renovations take to be completed?
A: It is anticipated works will be completed and the venue re-opened in 
September 2021. This timeframe allows for any additional works which may occur due to savings obtained throughout the project. If completion occurs earlier, the hall will be reopened for use as soon as practical. 

Q: What are the disruptions to ​the public?
A: Gatton Shire Hall will be unavailable to book for the duration of the works. Availability of off-street parking adjacent to the Hall will be reduced by approximately 10 bays which are part of the construction zone. Some off-street roadways may be disrupted from time to time with appropriate signage displayed with as much notice as possible, but sometimes that may be very limited.

Q: Can we still hold an event in Centenary Park?
A: Yes, the public are still able to hold events in the Centenary Park but need to be made aware of the works happening at the Gatton Shire Hall and possible construction noise. 

Q: What are the positive impacts of this work?
A:
  • Local cafés & shops will benefit from contractor’s expenditure throughout the construction period. 
  • A renovated hall for community use upon completion. 
  • Increased revenue for local contractors and suppliers who are engaged for services by the Principal Contractor.
  • A $2.08M project only costing Council (and therefore ratepayers) $0.527M.
  • A major community venue that will meet local requirements for many years.​